Aug-28-2008
 

Engineering Public Works Projects 2002-2003

This is a comprehensive listing of the capital improvement projects for Public Works for this fiscal year (2002-2003).  The listing is organized by department: Sewer, Storm, Streets and Water.  It does not represent the daily maintenance each department performs, only the capital projects projected for the fiscal year.  

Questions about these projects can be directed to the Engineering Director or Operations Supervisor for each department:

Department Supervisor Phone E-mail
Engineering Paul Shirey 503-786-7601 shireyp@ci.milwaukie.or.us
Sewer Jack Perry 503-786-7615 perryj@ci.milwaukie.or.us
Storm Jack Perry 503-786-7615 perryj@ci.milwaukie.or.us
Streets Mike Clark 503-786-7617 clarkm@ci.milwaukie.or.us
Water Jay Saatkamp 503-786-7616 saatkampj@ci.milwaukie.or.us

 

Sanitary Sewer

CIP
  • Implement final phase of volume based sewer rates 
  • Sewer line replacement project (select locations) 
  • Portland rate transition project
Private Development
  • Implement final phase of volume based sewer rates 
  • Sewer line replacement project (select locations) 
  • Portland rate transition project

Storm

CIP
  • 40th and 43rd Storm Project 
  • Prepare request for proposal for Master Plan update
Facilities
  • Tuck Wash at JCB- utility design
Development Review
  • Wister St. Improvement (Frick) 
  • Electra Credit Union public improvements 
  • Maplewood Subdivision 
  • King Road Commercial Center (Dieringer's)

Streets

CIP
  • McLoughlin Blvd. Improvements Project (Reconciled ROW issues w/FHWA and ODOT, prepared RFP/advertised/began contract negotiations for design contract) 
  • Johnson Creek Blvd. phase III (prepared staff reports and coordinated with CC for intergovernmental agreements for ROW acquistion and final construction) 
  • Lake Road Sidewalk Imp. Project (worked w/Streets Dept. to pave an asphalt concrete walking path on the south side of Lake Road just west of Rowe Middle School) 
  • Phase 1 of Transportation SDC Project (initial evaluation of deficiencies in preparation for resolution code change)
Non-CIP Grant Applications For:
  • ODOT Bike/Ped, 42nd Ave Improvements, JCB-Olsen (Awarded) 
  • Clack. Cnty. CDBG (supplemental to existing grant), for King, 37th & 40th Ave. Improvements (Awarded) o MTIP, Lake Road and Intelligent Transportation Systems (not awarded) 
  • ODOT Transportation Enhancement, Main Street Demonstration Project (not awarded)
Development Review or Other Special Projects
  • Downtown Parking/Traffic Management Plan (Sept. 02 - June 03) 
  • Waldorf School, 21st and Harrison (including Traffic Impact Study evaluation) 
  • Maplewood Subdivision (Centex Homes), south of Lake between Vernie and Where Else Lane (including Traffic Impact Study evaluation) 
  • King Road Commercial Center (Dieringer's), o Liaison to the Traffic Safety Board (duties ended December 02) 
  • Provide support for review of TCDR, drafting traffic regulations, and evaluation of NTMP requests 
  • Technical support for the NILUS Project and the South Corridor Project.
 

Water

CIP
  • Portland Metered Water Intertie 
  • Replacement Design for Monroe St.(42nd to 52nd) & Franklin St. (42nd to 45th) 
  • Lava Drive Booster Pump Station Replacement Design 
  • Replacement design for Logus Rd & Harlow St o Water Rate Study 
  • Water Cost of Service Study 
  • Wellhead Survey
Private Development
  • Hillside Park sidewalks o Wister St. Improvement (Frick) 
  • Waterline extension in front of Bob's Red Mill 
  • Electra Credit Union public improvements 
  • King Road Commercial Center (Dieringer's)


Last updated: 04/17/08
 